Construction progress
1. 7. 2017
Photos of the completed project (july)
> >
7. 12. 2016
Photos of the completed project (december)
> >
17. 10. 2016
Photos of the completed project (october)
> >
4. and 5. 10. 2016
Final works just before the final approval of the project.
> >
8. 9. 2016
Final works on terraces and laying a lock pavement.
> >
25. 8. 2016
Final works on the interiors + terraces and balconies.
> >
9. 8. 2016
The installing floating floors and finishing work of balcony.
> >
21. 7. 2016
The installing weatherization and interior tiles.
> >
8. 7. 2016
Laying interior tiles and sanitation.
> >
15. 6. 2016
Laying underfloor heating and interior tiles.
> >
1. 6. 2016
Flood testing and final works on the facade.
> >
20. 5. 2016
Final works on the facade.
> >
9. 5. 2016
The works on the facade continue.
> >
2. 5. 2016
Moulding anhydrite floors and areal distribution networks.
> >
25. 4. 2016
Moulding anhydrite floors, finishing facades.
> >
6. 4. 2016
The works on facades and building insulation.
> >
24. 3. 2016
The works on facades and the installation of waterproofing inside the atrium continue.
> >
19. 3. 2016
The construction continues with facades work and the installation of waterproofing inside the atrium.
> >
3. 3. 2016
The installing of windows is almost completed. The works continue with building partition walls.
> >