Unique living next to metro station 
and with fantastic view of Prague!

Construction progress

1. 7. 2017

Photos of the completed project (july)


7. 12. 2016

Photos of the completed project (december)


17. 10. 2016

Photos of the completed project (october)


4. and 5. 10. 2016

Final works just before the final approval of the project.


8. 9. 2016

Final works on terraces and laying a lock pavement.


25. 8. 2016

Final works on the interiors + terraces and balconies.


9. 8. 2016

The installing floating floors and finishing work of balcony.


21. 7. 2016

The installing weatherization and interior tiles.


8. 7. 2016

Laying interior tiles and sanitation.

 


15. 6. 2016

Laying underfloor heating and interior tiles.

 


1. 6. 2016

Flood testing and final works on the facade.


20. 5. 2016

Final works on the facade.


9. 5. 2016

The works on the facade continue.


2. 5. 2016

Moulding anhydrite floors and areal distribution networks.


25. 4. 2016

Moulding anhydrite floors, finishing facades.


6. 4. 2016

The works on facades and building insulation.


24. 3. 2016

The works on facades and the installation of waterproofing inside the atrium continue.


19. 3. 2016

The construction continues with facades work and the installation of waterproofing inside the atrium.


3. 3. 2016

The installing of windows is almost completed. The works continue with building partition walls.


26. 2. 2016

The installing of windows in the third and fourth floors has been started.


18. 2. 2016

Rough construction is completed!


5. 2. 2016

The installing of windows continues.


29. 1. 2016

The installing of windows in the second floor has been started.


26. 1. 2016

Finishing works on the fifth floor.


21. 1. 2016

The construction continues with finishing works on the fifth floor and the installing of windows in the first floor has been started.


 

11. 1. 2016

Construction of the fifth floor above ground continues.

 


29. 12. 2015

We have begun the construction of the fifth floor.


 

21. 12. 2015

The fourth floor is almost complete.


 

7. 12. 2015

We are finishing the third floor and we have begun the construction of the fourth floor


 

20. 11. 2015 and 22. 11. 2015

Construction of the third floor above ground continues


 

10. 11. 2015

We are finishing the second floor and we have begun the construction of the third floor


 

2. 11. 2015

We are finishing the second floor and we have begun the construction of the third floor


 

22. 10. 2015

Construction of the second floor above ground continues


 

14. 10. 2015

Reinforcing and boarding of the second floor


 

8. 10. 2015

Construction of the first floor above ground continues


 

1. 10. 2015

Reinforcing and boarding of the first floor


 

17. 9. 2015

Concreting of the first floor and atrium


 

31. 8. 2015

Formwork and reinforcement of the first underground floor


 

24. 8. 2015

Concreting of the first underground floor


 

3. 8. 2015

Concreting of the second underground floor


 

24. 7. 2015

Unique photos of construction from the bird's eye view


 

22. 7. 2015

Formwork and reinforcement of the second underground floor


 

9. 7. 2015

The second crane on the construction site


 

30. 6. 2015

The first crane on the construction site


 

25. 6. 2015

Reinforcement of the base plate of garages and section C4 - 2nd underground floor, assembly of building crane, casting of the concrete base section C3 and C2


 

22. 6. 2015

Concreting of the base plate (sections D1 and D2)


 

16. 6. 2015

Reinforcement of the base plate section D1 and D2 - 2nd underground floor


 

8. 6. 2015

Start the construction of our project


 

17. 4. 2015

Excavation work successfully continues


 

9. 4. 2015

Building construction pit


 

19. 3. 2015

Excavation works


 

16. 2. 2015

Building construction pit - drilling of stilts


 

20. 1. 2015

Demolition of current objects - underground floors


 

19. 12. 2014

Demolition work almost finished


 

25.11.2014

Demolition continues


 

14.11.2014

Demolition of current objects


 

25.10.2014

Demolition of current objects on our ground in Kobylisy was started.