Construction progress
1. 7. 2017
Photos of the completed project (july)
7. 12. 2016
Photos of the completed project (december)
17. 10. 2016
Photos of the completed project (october)
4. and 5. 10. 2016
Final works just before the final approval of the project.
8. 9. 2016
Final works on terraces and laying a lock pavement.
25. 8. 2016
Final works on the interiors + terraces and balconies.
9. 8. 2016
The installing floating floors and finishing work of balcony.
21. 7. 2016
The installing weatherization and interior tiles.
8. 7. 2016
Laying interior tiles and sanitation.
15. 6. 2016
Laying underfloor heating and interior tiles.
1. 6. 2016
Flood testing and final works on the facade.
20. 5. 2016
Final works on the facade.
9. 5. 2016
The works on the facade continue.
2. 5. 2016
Moulding anhydrite floors and areal distribution networks.
25. 4. 2016
Moulding anhydrite floors, finishing facades.
6. 4. 2016
The works on facades and building insulation.
24. 3. 2016
The works on facades and the installation of waterproofing inside the atrium continue.
19. 3. 2016
The construction continues with facades work and the installation of waterproofing inside the atrium.
3. 3. 2016
The installing of windows is almost completed. The works continue with building partition walls.